Navy Base Paint, Blast & Rubber Facility

Size

74,249 sf

Cost

$52M

Recruited for government design/build expertise, this project scope includes the following elements:

  1. Construct New Building: 74,249 sf

  2. Renovate 3 Existing Buildings: 52,727 sf

  3. Demolish 8 Buildings and Portions of 2 Buildings: 73,450 sf

The project scope includes all permitting, relocation of above and below ground utilities, railroad track demolition and relocation, full or partial demolition/renovation of 11 buildings, hazardous waste remediation (largely asbestos and lead-contaminated building elements), security (including Anti-Terrorism Force Protection design), and sustainable design requirements.

The new building and the portions of the existing buildings will be renovated and will consume far less energy than the current buildings, most of which are decades beyond their useful service life.

The new 74,249 sf building will house the following functions Rubber Manufacturing, Shaft Operations, Very Large Parts, Blast Operations, Paint Operations, Waterjet Operations, SHT Buffer Operations, Fiberglass Repair Operations, Plastisol, Linoleum/Carpet Operations, Consumable / Hazmat / Storage, and Administrative and Support Areas. Construction started Summer 2019 with 2023 finish date.